Fletcher Allen Health Care CVMC Kidney Dialysis Unit Renovation Project

L.N. Consulting, Inc. worked with Scott & Partners Architects in designing the renovations and expansion of the existing renal dialysis unit located at the Central Vermont Hospital. The project consisted of approximately 6,700 sq. ft. of renovation and included the design of the HVAC systems, dialysis unit water treatment systems and electrical systems. The project was completed under multiple phases while maintaining the operational status of the existing dialysis unit and support facilities.

Berlin, VT

Fletcher Allen Health Care, Mark Gilbert (802) 343-4699

Scott and Partners, Tyler Scott, (802) 879-5153

Farrington Construction

$2.0 million

Completed 2002