L.N. Consulting, Inc. worked directly for Central Vermont Hospital as the prime consultant for the HVAC Infrastructure Upgrade Project. The proposed HVAC Infrastructure Upgrade Project included the design and construction of a new 60,000 CFM air handler and support infrastructure to condition the second and third floors of the Central Vermont Hospital. The new air handler is housed in a penthouse constructed on the roof of the existing hospital. The existing programs supported by the proposed air handler are the ICU, Behavioral Health, Renal Dialysis, Respiratory Therapy, Birthing, Endoscopy, and Inpatient Services. The project was designed and phased to minimize air handler shutdowns. L.N. Consulting, Inc was the prime consultant and Mechanical and Electrical Engineer for the project.

Berlin, VT

Central Vermont Medical Center, Amy Slayton (802) 371 4100

Morris Switzer Environments for Health

E.F. Wall

$1.5 million

Completed 2004